{Date:3}{Start Time:4}-{End Time:5}8Location: Pheasant Ridge, 2279 - Lang
Task: OtherDoctors
{Date:3}{Start Time:4}-{End Time:5}7.5Location: Pheasant Ridge, 2279 - Lang
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}8Location: Pheasant Ridge, 2279 - Lang
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}5Location: Pheasant Ridge, 2279 - Lang
Task: 05 Siding
{Date:3}{Start Time:4}-{End Time:5}6.5Location: Pheasant Ridge, 2279 - Lang
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}7Location: Pheasant Ridge, 2279 - Lang
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}7Location: Torrey Pines, 2830 - Bryden Bathroom
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}6Location: Pheasant Ridge, 2279 - Lang
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}6.5Location: Monroe - 2957 - Petersen Window
Task: 09 Millwork & Trim 093 Exterior Doors
{Date:3}{Start Time:4}-{End Time:5}8Location: OtherEisenhower
Task: 03 Framing

Building steps, four hours Pheasant ridge, clean up his site

{Date:3}{Start Time:4}-{End Time:5}8Location: Pheasant Ridge, 2279 - Lang
Task: OtherScreens
{Date:3}{Start Time:4}-{End Time:5}8Location: Pheasant Ridge, 2279 - Lang
Task: OtherScreens
{Date:3}{Start Time:4}-{End Time:5}4Location: Pheasant Ridge, 2279 - Lang
Task: OtherMounting screen door and trim
{Date:3}{Start Time:4}-{End Time:5}1.5Location: Pheasant Ridge, 2279 - Lang
Task: OtherPicking up materials for down spouts, and hose with pvc under deck
{Date:3}{Start Time:4}-{End Time:5}5.5Location: Torrey Pines, 2830 - Bryden Bathroom
Task: 50 Plumbing

Under deck hose and down spouts

{Date:3}{Start Time:4}-{End Time:5}6.5Location: 550th, 28021 - Steve Carter DECK
Task: 03 Framing
{Date:3}{Start Time:4}-{End Time:5}8Location: 550th, 28021 - Steve Carter DECK
Task: 03 Framing
{Date:3}{Start Time:4}-{End Time:5}7Location: 550th, 28021 - Steve Carter DECK
Task: 03 Framing
{Date:3}{Start Time:4}-{End Time:5}8Location: 550th, 28021 - Steve Carter DECK
Task: 09 Millwork & Trim 093 Exterior Doors
{Date:3}{Start Time:4}-{End Time:5}8Location: 550th, 28021 - Steve Carter DECK
Task: 09 Millwork & Trim 093 Exterior Doors
{Date:3}{Start Time:4}-{End Time:5}7Location: OtherStonebrook
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}7Location: OtherStonebrook
Task: 09 Millwork & Trim

Disregard the stonebrook entry for the 17 th

{Date:3}{Start Time:4}-{End Time:5}8Location: OtherStonebrook
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}8Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}5Location: 550th, 28021 - Steve Carter BASEMENT
Task: 09 Millwork & Trim