{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: Pheasant Ridge, 2279 - Lang Task: OtherDoctors | |
{Date:3} | {Start Time:4}-{End Time:5} | 7.5 | Location: Pheasant Ridge, 2279 - Lang Task: 09 Millwork & Trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: Pheasant Ridge, 2279 - Lang Task: 09 Millwork & Trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 5 | Location: Pheasant Ridge, 2279 - Lang Task: 05 Siding | |
{Date:3} | {Start Time:4}-{End Time:5} | 6.5 | Location: Pheasant Ridge, 2279 - Lang Task: 09 Millwork & Trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 7 | Location: Pheasant Ridge, 2279 - Lang Task: 09 Millwork & Trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 7 | Location: Torrey Pines, 2830 - Bryden Bathroom Task: 09 Millwork & Trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 6 | Location: Pheasant Ridge, 2279 - Lang Task: 09 Millwork & Trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 6.5 | Location: Monroe - 2957 - Petersen Window Task: 09 Millwork & Trim 093 Exterior Doors | |
{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: OtherEisenhower Task: 03 Framing | Building steps, four hours Pheasant ridge, clean up his site … |
{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: Pheasant Ridge, 2279 - Lang Task: OtherScreens | |
{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: Pheasant Ridge, 2279 - Lang Task: OtherScreens | |
{Date:3} | {Start Time:4}-{End Time:5} | 4 | Location: Pheasant Ridge, 2279 - Lang Task: OtherMounting screen door and trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 1.5 | Location: Pheasant Ridge, 2279 - Lang Task: OtherPicking up materials for down spouts, and hose with pvc under deck | |
{Date:3} | {Start Time:4}-{End Time:5} | 5.5 | Location: Torrey Pines, 2830 - Bryden Bathroom Task: 50 Plumbing | Under deck hose and down spouts |
{Date:3} | {Start Time:4}-{End Time:5} | 6.5 | Location: 550th, 28021 - Steve Carter DECK Task: 03 Framing | |
{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: 550th, 28021 - Steve Carter DECK Task: 03 Framing | |
{Date:3} | {Start Time:4}-{End Time:5} | 7 | Location: 550th, 28021 - Steve Carter DECK Task: 03 Framing | |
{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: 550th, 28021 - Steve Carter DECK Task: 09 Millwork & Trim 093 Exterior Doors | |
{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: 550th, 28021 - Steve Carter DECK Task: 09 Millwork & Trim 093 Exterior Doors | |
{Date:3} | {Start Time:4}-{End Time:5} | 7 | Location: OtherStonebrook Task: 09 Millwork & Trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 7 | Location: OtherStonebrook Task: 09 Millwork & Trim | Disregard the stonebrook entry for the 17 th |
{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: OtherStonebrook Task: 09 Millwork & Trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 8 | Location: 4022 Stone Brooke - Helms - Master Suite Remodel Task: 09 Millwork & Trim | |
{Date:3} | {Start Time:4}-{End Time:5} | 5 | Location: 550th, 28021 - Steve Carter BASEMENT Task: 09 Millwork & Trim | The reason I only put 5 hours is , I … |