DateTimeHoursJobNotes
{Date:3}{Start Time:4}-{End Time:5}2Location: 412 26th - Slade - Roof
Task: 04 Roof Coverage/repair
{Date:3}{Start Time:4}-{End Time:5}2Location: Fletcher - 4024 - Jolly, Bob
Task: 09 Millwork & Trim 098 Cabinets & Vanities
{Date:3}{Start Time:4}-{End Time:5}1.5Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 03 Framing
{Date:3}{Start Time:4}-{End Time:5}3.25Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 02 Demo
{Date:3}{Start Time:4}-{End Time:5}2Location: Fletcher - 4024 - Jolly, Bob
Task: 02 Demo
{Date:3}{Start Time:4}-{End Time:5}5Location: Fletcher - 4024 - Jolly, Bob
Task: 02 Demo
{Date:3}{Start Time:4}-{End Time:5}1.5Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 02 Demo
{Date:3}{Start Time:4}-{End Time:5}2Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 03 Framing
{Date:3}{Start Time:4}-{End Time:5}2.5Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 02 Demo
{Date:3}{Start Time:4}-{End Time:5}1.5Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 02 Demo
{Date:3}{Start Time:4}-{End Time:5}3Location: Fletcher - 4024 - Jolly, Bob
Task: 02 Demo
{Date:3}{Start Time:4}-{End Time:5}2Location: Fletcher - 4024 - Jolly, Bob
Task: 02 Demo
{Date:3}{Start Time:4}-{End Time:5}3.125Location: OtherStahr
Task: OtherDoor
{Date:3}{Start Time:4}-{End Time:5}2Location: Hyde - 3809 Addition - Dunn
Task: 10 Cleanup
{Date:3}{Start Time:4}-{End Time:5}2Location: Hyde - 3809 Addition - Dunn
Task: 06 Insulation
{Date:3}{Start Time:4}-{End Time:5}3.5Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}2.5Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}4Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}2.75Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 02 Demo
{Date:3}{Start Time:4}-{End Time:5}3Location: Hyde - 3809 Addition - Dunn
Task: 09 Millwork & Trim 098 Cabinets & Vanities
{Date:3}{Start Time:4}-{End Time:5}3Location: Hyde - 3809 Addition - Dunn
Task: 09 Millwork & Trim 098 Cabinets & Vanities
{Date:3}{Start Time:4}-{End Time:5}3Location: Hyde - 3809 Addition - Dunn
Task: 09 Millwork & Trim 098 Cabinets & Vanities
{Date:3}{Start Time:4}-{End Time:5}7Location: OtherGetting van
Task: OtherGetting van
{Date:3}{Start Time:4}-{End Time:5}4.5Location: 4022 Stone Brooke - Helms - Master Suite Remodel
Task: 09 Millwork & Trim
{Date:3}{Start Time:4}-{End Time:5}3Location: Cessna - Tjaden, Kristen & Kurt
Task: 09 Millwork & Trim 093 Exterior Doors